Fjerning offshore
I juli 2016 fjernet AF Offshore Decom og våre underentreprenører overstellet på plattformen på 14 dager.
By using innovative methods, AF has removed one of the largest platforms in the North Sea.
I juli 2016 fjernet AF Offshore Decom og våre underentreprenører overstellet på plattformen på 14 dager.
Verdens to største lastefartøyer fraktet toppen av plattformen inn til AF Miljøbase Vats utenfor Haugesund. Her ble den klippet opp og plattformen kildesortert.
Stålunderstellet på plattformen fjernes og fraktes inn til AF Miljøbase Vats.
The contract included engineering, preparatory works, removal, and recycling (EPRD) of both the decks and steel foundations. Demolition and recycling were carried out in the UK and at the Environmental Base in Vats.
British continental shelf east of the Shetland Islands
The Murchison field straddled the British–Norwegian boundary, with the platform located on the British continental shelf east of the Shetland Islands. One of the largest steel jacket platforms in the North Sea, Murchison had been in operation since 1980 before production ceased in March 2014.
AF Gruppen’s wholly owned subsidiary, AF Decom Offshore U.K. Limited, together with Heerema Marine Contractors Nederland SE (forming the Heerema–AF Consortium), entered into an agreement with Canadian Natural Resources International (U.K.) Limited (CNR) for the removal and recycling of the Murchison platform.
Heerema and AF Gruppen had a long-standing record of successful collaboration on North Sea removal and recycling projects, delivering strong HSE performance, technical excellence, and predictable execution.
With 130 offshore employees at any given time, challenging weather, costly equipment, and strict HSE requirements, the project demanded meticulous planning. Early in the process, the team proposed an innovative solution: deploying two of the world’s largest heavy-lift vessels to remove the platform more efficiently and safely—a “Two-Vessel Scenario” never before attempted.
Summer 2016: The platform’s topside was removed and transported to the Environmental Base at Vats within just three months.
Spring 2017: The substructure was dismantled, and recycling continued toward a target of 96% material recovery.
The project was completed in 2020—one year ahead of schedule—and was executed without any injuries
Ricky Ryttmar
Project Director
AF Offshore Decom AS