Decommissioning of a floating storage unit

Engineering, receipt, cleaning, dismantling and recycling of the Alba Floating Storage Unit (FSU) from the UK sector of the North Sea.

Project status

      Feb 2026
      Dec 2027

      The Alba FSU project includes the complete decommissioning process from engineering and project preparation through to cleaning, dismantling and recycling. 

      • 24,000

        Tons

      • 350-400

        MNOK

      AF Gruppen

      The Scope

      In the initial phase, the asset will remain moored at the quay at the base for preparatory work and later marine operations before being brought ashore at the end of 2027. Load-in will be carried out using the same method applied when an FPSO was brought ashore in 2022, with a submersible barge and modular trailers. This is known as the float-on load-in method.

       

      When completed, the Alba FSU project will add to AF's track record in delivering large-scale offshore decommissioning projects and strengthen its position as a leading provider of integrated engineering, decommissioning and recycling services.

      Project info

      Project type: Removal and recycling offshore
      Customer: Ithaca Energy
      Contract type: EPRD