Decommissioning of a floating storage asset

Engineering, receipt, cleaning, dismantling and recycling of the Alba Floating Storage Unit (FSU) from the UK sector of the North Sea.

Project status

      Feb 2026
      Dec 2027

      The Alba FSU project includes the complete decommissioning process from engineering and project preparation through to cleaning, dismantling and recycling.

      • 24,000

        Tons for recycling

      • MNOK 350-400

        Value

      AF Gruppen

      Raunesvegen 597, 5578 Nedre Vats

      The Scope

      The Alba Floating Storage Unit (FSU) has been a key part of the UK Central North Sea for more than 30 years and represents one of our most significant decommissioning projects. Following removal from the field, the vessel will undergo a phased programme of marine operations, load-in, dismantling and responsible recycling.

      During the initial phase, the vessel will remain alongside the quay while preparatory works and marine operations are completed ahead of load-in. The Alba FSU will then be brought ashore using our  proven float-on load-in methodology, successfully demonstrated on the Curlew FPSO project, where a submersible barge and modular transporters are used to transfer the asset safely onto the quayside.

      Once complete, the project will further strengthen our position as a leading provider of offshore decommissioning and recycling services, building on experience gained from other major projects including Curlew FPSO, Janice A, Brae B, Dunlin Alpha and Eider.

       

      Project info

      Project type: Removal and recycling offshore
      Customer: Ithaca
      Contract type: Onshore dismantle and recycling (not an offshore removal project).
      Entrepreneur: