Important milestone
With around 300 guests present, the enormous machine bored through the final section of rock and emerged into a festively decorated cavern at Huseby. Workers stepped out of the machine carrying Norwegian, Italian and Portuguese flags, greeted by cheering colleagues offering hugs and congratulations. An important milestone in a major project had been reached.
The 11‑kilometre tunnel, now fully excavated, is a central part of Oslo’s new water supply system. Oslo Municipality, through the Water and Sewerage Authority, is the client for the project.
«All of the approximately 40 kilometres of tunnelling in the project have now been completed. We are very pleased that this complex tunnelling work has been carried out faster than planned, within budget, and most importantly without serious injury to people or the environment,» says Anna Maria Aursund, Director of the Water and Sewerage Authority.