The contract includes the installation of gas and compressed air systems at the new Aker Hospital, which covers an area of approximately 170 000 square meters. The agreement is valued at around NOK 200 million excluding VAT and will be carried out as a turnkey contract. Planning work will commence immediately after the end of the required qualifying period. Production is expected to start in the second quarter of 2026, with completion anticipated in the fourth quarter of 2029.

“The new hospital will represent a significant improvement in healthcare services for the region’s population, and AF Gruppen is pleased to have been awarded another contract in this project. We now look forward to delivering functional solutions in close collaboration with the project organization at Helse Sør-Øst RHF at the new Aker Hospital,” says Eirik Wraal, EVP at AF Gruppen.