Demolition phase II in Sunndalsøra

Demolition and environmental clean-up of two large electrolysis halls, in connection with the expansion of SU 4.

The halls had a size of approx. 45 x 500 m, containing together a total of 300 electrolysis furnaces, were torn down selectively. The EE waste as well as other environmentally hazardous substances were dismantled manually, before the demolition machinery was brought in. All PAH-contaminated dust was removed from the structures before the demolition could start. The material of the furnaces (approx. 15,000 tons) was contaminated and was transported to Langøya for deposition. Reinforcement was separated from the concrete, which was crushed to a 0-200 mm fraction and recycled.

Project type Demolition
Timespan September 2002 - April 2003
Customer AF Sunndal / Norsk Hydro
Project address Romsdalsveien 4
Contract practice Turnkey contract
Contractor AF Decom Onshore
Volume Approx. 25,000 tons of steel and 100,000 tons of PAH-contaminated concrete, 300 tons special waste and 80 tons of asbestos.

AF Gruppen

AF Gruppen is one of Norway's leading contactor and industry group, covering a wide range of services.

Country

Businessarea