Landfall Tunnel Kollsnes

AF has performed landfall tunnel system and riser packages at Kollsnes for A/S Norske Shell.

Tunnel system of 7.5 km for gas pipeline from treatment plant at Kollsnes to a connection point 200 m below sea level and 3.6 km offshore.

The contract also included the engineering and installation of qty. 2 450 ton riser packages. These where assembled in the shafts in connection with the tunnels, 165 m below sea level..

Project type Offshore & Civil Construction
Timespan January 1991 - December 1995
Customer A/S Norske Shell
Project address Kollsnes
Contract size NOK 480 mill.
Contract practice General contract
Contractor AF Anlegg Oil & Gas (75% of project consortium)
Volume Tunnels: 7.5 km, Riser packages: 2, each 450 metric ton