Large construction contract to AF
AF Gruppen is nominated by the EB Kraftproduksjon AS as contractor for the development of the new water power plant Embretsfoss 4 in Modum, Buskerud.
The agreement has a value of MNOK 230 excluding VAT. The work includes civil works. Planned start is January/February 2010 and completion is during first
half of 2013.
- This is an important project for our civil engineering operations. Civil works for water power plants are an important part of AFs history, and we have ambitions to be a significant party in developing renewable energy. We are therefore proud
to have won a challenging project, and we look forward to working with EB Kraftproduksjon", says Pål Egil Rønn, CEO of AF Gruppen.
For further information:
CEO: Pål Egil Rønn, tel. 90 95 77 13
Director civil engineering: Arild Moe, tel. 91 37 62 65
Publisert:12/18/2009